WELLINGBOROUGH NEW PRISON

Burgess Associates were recommended to an Electrical labour only contractor undertaking installation works on 2 blocks at the New Wellingborough Prison.

The project was well on and reaching practical completion but the Electrical Contractor had a significant change account which was not agreed or in some cases was at budget status.

Burgess Associates worked closely with our client and the Principal MEP contractor to measure, value, submit and agree the change account and revised sub contract completion date.

As a result of this a fair and reasonable settlement was reached and our clients ongoing working relationship remains.